Contract Agreement For Construction Of House

The total cost of the building – Rs. 70.67,000 (five thousand rupees only) (Fill the total cost of the building) work relating to the entire construction of this building according to the architectural and structural designs and according to the elements indicated and signed in the calendar (Fill the date of the signature). (Any additional work is paid for at the above rates). Information on the type of materials used for construction should be included in the agreement. a) All materials and treatments must be the best of each type and be described in calendars. The architect`s decision regarding the sets, quantities and scope of the material and treatment is final and binding for the contractor. Specific marks indicated according to the attached schedule. Risk factors should be included in the contract to protect the interests of the owner. If you do not read the written agreement, you will not be in a defensive position. The supply of products and services is mentioned in the contract between the owner and the contractor.

If the agreement is signed, it cannot be amended at a later date, unless it is agreed by both parties. Contractual conditions that are useful to both parties (owners and civil contractors) must be satisfied. If you are not satisfied with the terms of the contract, you should be able to negotiate with the contractor. 4. The owner pays the builders a sum of Rs…………. whose owner pays each week to the owners the amount that can be sufficient to cover the costs incurred by the owners for the materials used in the works, verified and certified by the architect, Rs…… on the architect`s certificate that the work is completed up to the first floor, the additional sum of Rs ………… on the architect`s certification that the work is completed and that the balance must be paid on the architect`s certificate, that the above works have been completed in all respects in accordance with the agreement and that the owners have, at their own expense, removed all scaffolding, fencing, materials and unused waste from the premises and managed the bungalow for immediate use and use and management. However, an amount equal to 5% of the total amount of the contract payable by the owner under this contract is withheld by the owner as a deduction allowance which, after a period of 12 months from the date of delivery of that bungalow, is fully due and is due for occupancy.

The owners agree and undertake to remedy any defects that can be found or found during the 12-month period. If the owners do not correct the defects found or refuse to correct the defects found by the owner within a fortnight of the date of notification to the owners, the owner has the right to have these defects corrected by other agencies that he deems appropriate for all the costs and risk of the owners and to use the deduction allowance; To the extent that, in the event of insufficient deduction pay in question, the costs, costs and expenses incurred by the owner to remedy the construction defects are not sufficient, the owners must correct the defect within 7 days of the owner`s written request, otherwise the owners are required to pay the same amount as the interest of 15% per year.